Major Renovations to MARTA’s Five Points Station, Where All Transit Lines Intersect

MARTA, the principal public transport operator in Atlanta, Georgia, has partnered with Carroll Daniel | Moody to complete major renovations to Five Points Station. Five Points is at the heart of downtown Atlanta and the transfer point between all rail lines.

marta-five-points-operational

Working in an Operational Transit Station

Since Five Points Station is open and operational during construction, our project team must have ongoing coordination and communication with the operations team to ensure the safety of the project teams, subcontractors, MARTA employees and passengers. In addition to safety, patron access to the station throughout construction is a priority. Any work that will change patron access to areas in the station must be coordinated and approved by MARTA in advance. Alternate routing via signage and barricades must be provided to guide patrons safely around the work and to their destination. To prioritize safety & patron access, the project is broken into almost 40 phases that are sequenced in a manner that minimizes impact to the station.

website case studies squareish

Project Overview

Working within an operational transit station, Carroll Daniel | Moody’s scope of work at Five Points Station includes:

· Replacing existing brick pavers with new porcelain tile pavers throughout the three-story station.

· Replacing seating benches and trash receptacles.

· Installing new metal panel ceilings with decorative trim, including relocation of low-voltage devices and signage.

· Restoring the historic Eiseman Façade within the station.

· Installing new wall tile and metal wall panels.

· Painting metal wall slats and cleaning and sealing granite wall panels.

· Replacing acoustical sound panels in the track wells.

· Upgrading all lighting to new LED fixtures.

· Installing four high-volume fans.

Project Planning

With work occurring above or adjacent to the tracks, track closures are sometimes necessary. In order to close one track for work, MARTA must operate trains in both directions through the station on a single track as to minimize disruptions to passengers. These “single-track events” must be coordinated with rail control six months in advance and planned around normal maintenance activities and projects at other stations. During single tracking, our work must be performed around the clock – typically taking between 26 and 54 hours over a weekend.

interior shot of a MARTA station with a rail car

Accessing and Bringing Materials to the Sites

The Five Points Station has four levels, with our team working on the first two levels for this project. The only access from the streetside is via passenger elevators, stairs, and escalators; for bulk and heavy materials and equipment, these must be brought in on the tracks via a MARTA locomotive or Hi-Rail vehicle. To mitigate this obstacle, our project team has invested in a truck fit with equipment that allows it to operate on the rails – easing the material delivery process.

Restoring History

The Carroll Daniel | Moody project team coordinated the installation of a scaffolding structure that will span both tracks on the North/South platform and extend vertically to three levels of the station. The top of this structure will hold a platform that will serve as a containment area. At the two levels below, the scaffolding will be used to restore the historic Eiseman Façade found inside the station. The Eiseman Façade is the face of an old building that was located where Five Points station is now. This façade was salvaged and then rebuilt inside the station and will be cleaned and repaired in this project to restore it to its original condition.

Related Case Studies

MARTA Station Rehabilitation Program
Indian Creek Station
Station Renovation
As part of the MARTA Station Rehabilitation Program, Carroll Daniel | Moody, A Joint Venture, is completing major renovations at Indian Creek Station.
MARTA Station Rehabilitation Program
College Park Station
Paver Replacement Project
Carroll Daniel | Moody, A Joint Venture, continues work on the MARTA Station Rehabilitation Program at College Park Station on the Paver Replacement Project.
interior image of scissor lifts at delta ticketing counter in hartsfield-jackson atlanta international airport
Hartsfield-Jackson Atlanta International Airport
Domestic Terminal
Interior Enhancement Project
Carroll Daniel Construction has been working at the Hartsfield-Jackson Atlanta International Airport on the Domestic Terminal Interior Enhancements Project.
Delta Air Lines
Technical Operations Center
Renovation Projects
Carroll Daniel has been selected to work on multiple renovation and refresh projects at Delta’s Technical Operations Center building.
plane docked at a terminal at hartsfield-jackson atlanta international airport
Hartsfield-Jackson Atlanta International Airport
Concourse T
Fire Life Safety Enhancements Project
The Concourse T Fire Life Safety Enhancements Project was a renovation to the fire alarm, egress paths, security access systems, and existing structural systems that brought the concourse into compliance with the requirements of the most recent building, life safety, and fire protection codes.