From Preconstruction to Completion

Carroll Daniel Engineering provided preconstruction services to develop scope, cost and schedule for Accoya USA’s first manufacturing plant in the United States. The project was a joint venture between Eastman and Accsys Technologies PLC to manufacture a sustainable, high strength wood product. Once preconstruction was complete, Carroll Daniel Engineering moved into the engineering and procurement phases. The plant is located inside the Eastman Chemical complex.

Transcontinental Transport of Equipment

Key process equipment was procured from Western Europe including two large reactors that required significant logistics planning as they were shipped from Germany, through the Mobile, AL, port through a 700-mile journey via barge and over the road to Kingsport, TN.

Related Case Studies

Specialty Paper Mill Hardwood Fiberline
Glatfelter partnered with Carroll Daniel Engineering on the installation of a new hardwood fiberline and oxygen delignification system at their Spring Grove, Pennsylvania facility.
Advanced Packaging Facility
Following a fire that destroyed most of their 237,000 SF Advanced Packaging Solutions plant, Pactiv Evergreen turned to Carroll Daniel Engineering for a engineering services.
Iron Oxide Pigments Production Plant
Carroll Daniel Engineering provided engineering and procurement services for the 80-acre site and production facility.
TWEEL Manufacturing Facility
Michelin selected Carroll Daniel Engineering to provide engineering services for a TWEEL Manufacturing Facility in South Carolina.
Modular Carpet + Tile Manufacturing Facility
Interface selected Carroll Daniel Engineering to provide engineering services for a two-phase expansion to the center of their operations in LaGrange, Georgia.
Carbon Fiber Manufacturing Facility
Carroll Daniel Engineering was chosen to provide engineering services on a new carbon fiber facility in South Carolina that is part of a $600 million planned investment to supply automotive operations in the United States.