Taking it to Another Level

Expanding upward – inside an existing building.


The most challenging portion of this project involved building a new “KIPP to College” second floor addition within an existing building. The project team had to carefully work inside the existing lower level to provide the foundation and support needed for the new interior second floor. Steel had to be erected and concrete poured within the indoor, elevated space, with all materials and equipment going through the first floor and up 15 feet.

22-02-17_105

KIPP to College

Building communities.


Carroll Daniel looks for ways to give back to the communities in which we work. Despite the fact that nationally, only 10% of low-income students of color graduate from college, over 80% of KIPP students pursue a college degree after high school. In honor of the KIPP to College expansion and our outstanding partnership with this program and its founders, we created the Ra’Chel Ford Scholarship Fund, giving $5,000 to a deserving KIPP student who plans to pursue a college education.

The Carroll Daniel team has been an amazing partner for KIPP Metro Atlanta Schools from the beginning phases of this project through completion. From preconstruction through close-out, they have exemplified professionalism, expertise, common-sense judgment, and creativity.

Ra’Chel Ford
Managing Director of Regional Operations
KIPP Metro Atlanta Schools

Related Case Studies

KIPP Atlanta Collegiate Expansion & Renovation

Building strong foundations in the heart of Atlanta on an occupied campus.

Read More

East Forsyth High School

Carroll Daniel continued its partnership with Forsyth County Schools to construct the new East Forsyth High School, a 431,366 square-foot…

Read More

Seckinger High School

Carroll Daniel partnered with Gwinnett County Public Schools to build Seckinger High School, a new four-story, 510,000 SF building on…

Read More

Loganville Elementary School

Loganville Elementary School is a new elementary school on a 98-acre site. The project included artificial turf play fields and…

Read More

Mike and Lynn Cottrell Junior Achievement Discovery Center at North Georgia

The Mike and Lynn Cottrell Junior Achievement Discovery Center at North Georgia is a state-of-the-art learning facility that allows students…

Read More

Rabun Gap-Nachoochee School – Richard and John Woodruff Dining Hall

A beautifully crafted new dining hall for a private college preparatory school located in the Appalachian Mountains.

Read More

Alliance Academy for Innovation + New Parking Deck

The Alliance Academy for Innovation is Forsyth County Schools’ first STEM high school. A second phase of construction included adding…

Read More

Enota Multiple Intelligences Academy

The Enota Multiple Intelligences Academy project involved tearing down a 60 year-old school and building a new 129,000 SF, two-story,…

Read More

Discovery High School

The award-winning Discovery High School project consisted of taking an old Bridgestone tire warehouse and significantly altering it into a…

Read More

Gwinnett School of Mathematics, Science & Technology

A new five-story building and renovations to an existing, adjacent elementary school on an occupied and active campus.

Read More

Pine Street Elementary School

A brand new colorful elementary school with an impressive “wing design.”

Read More

Hilsman Middle School

A new two-story, 180,531 SF middle school constructed within a 14 month schedule.

Read More

See More Case Studies